62 of 65 AMRUT Projects Under Execution in J&K, None Yet Functional: Govt Tells House

62 of 65 AMRUT schemes under execution in J&K: Govt informs House

‘No scheme has been made functional yet’

Srinagar, Feb 20: The government on Friday informed the House that 65 Water Supply Schemes have been sanctioned for the Union Territory of Jammu and Kashmir under AMRUT 2.0, including one scheme for the Sopore constituency.

Advertisement

In response to a query by MLA Irshad Rasool Kar, the Chief Minister, who is also the Minister in charge, told the House, as per the news agency —Kashmir News Observer (KNO), that 62 of the sanctioned schemes are currently at various stages of execution.

The minister further informed that no scheme has been completed or made functional so far, adding that the technical evaluation has been completed for the Water Supply Scheme Sopore and Water Supply Scheme Udhampur Part I.

The Chief Minister also informed that Water Supply Scheme Udhampur Part II and Pokhribal Part II are at the evaluation stage, while the development of the AMRUT Model Pocket 24×7 has been re-tendered.—(KNO)

KSA Web Desk
KSA Web Deskhttps://kashmirstudentalerts.com
Stay Updated, Stay Simple: Get the Latest News with Ease at Kashmir Student Alerts
RELATED ARTICLES

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Trending